Question 37

Which of the following is MOST commonly associated with the WBS and used to develop a project timeline?

Options:

A.

Process diagram

B.

RACI matrix

C.

Gantt chart

D.

Network diagram

Question 38

During a project, the purpose of examining the cost baseline is to:

Options:

A.

organize payment of the bills

B.

determine the minimal cost of the project

C.

anticipate the total planned costs

D.

compare against the total planned income

Question 39

Which of the following project team members would MOST likely be tasked with maintaining project documents?

Options:

A.

Project coordinator

B.

Project manager

C.

Project scheduler

D.

Project sponsor

E.

Project champion

Question 40

An individual is responsible for the training and education for a new product in a strong matrix organization. Which of the following roles does this describe?

Options:

A.

Functional manager

B.

Project coordinator

C.

Project manager

D.

Champion