CompTIA Project+ Exam Questions and Answers

Question 101

Which of the following charts is a graphical representation of the causes of a specific event?

Options:

A.

Histogram

B.

Scatter

C.

Fishbone

D.

Gantt

Question 102

Which of the following inherently affects quality standards?

Options:

A.

SLA

B.

MOA

C.

MOU

D.

WBS

Question 103

A project manager would like to bring vendors into a new project. Which of the following documents should the potential vendors submit so the project manager can find the best vendors for the project?

Options:

A.

SLA

B.

SOW

C.

Change request

D.

RFP

Question 104

Which of the following events would MOST likely trigger communications to the largest audience for a given organization?

Options:

A.

Business continuity response

B.

Quality audit

C.

Replacement of a subcontractor

D.

Completion of a task