Question 41

A project sponsor wants to know when the plan changed to ship the deliverables to a new location. To determine the answer, the project manager should FIRST review the:

Options:

A.

project management plan

B.

scope statements and issue log

C.

project dashboard and status report

D.

action items and meeting minutes

Question 42

Communication on a project is flowing well. Team members are motivated, and they are allowed to make decisions about their work.

Which of the following management styles is the project manager MOST likely using?

Options:

A.

Exploitive

B.

Retrospective

C.

Participative

D.

Authoritative

Question 43

A project sponsor wants to demonstrate progress on a deliverable to all stakeholders at the next tollgate meeting. This feature was not scheduled for this tollgate, but the project manager plans to add it to the next phase. Which of the following describes what the project manager is doing?

Options:

A.

Crashing the schedule

B.

Prioritizing tasks

C.

Determining milestones

D.

Developing sprints

Question 44

Which of the following documents should the project manager complete if requirements have been defined, but neither a vendor nor a platform has been identified?

Options:

A.

RFP

B.

RFQ

C.

RFI

D.

SOW

Page: 11 / 30