Winter Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

IIBA CBAP Actual Questions

Page: 21 / 37
Total 497 questions

Certified Business Analysis Professional Questions and Answers

Question 81

You are the business analyst for your organization. For the past several months you have been completing the business analysis duties for the solution stakeholders. You now have, you believe, the solution requirements

identified and documented.

What must you now do with the requirements before proceeding?

Options:

A.

Make certain the stakeholders can pay for the solution and have them sign off on the requirements.

B.

Present the solution to the project manager for his input.

C.

Get all of the stakeholders to sign off on the requirements.

D.

Make certain the stakeholders understand the requirements before they approve the requirements you've gathered.

Question 82

What element of the conduct elicitation activity is tracked to provide a basis for future planning?

Options:

A.

Time actually spent eliciting the requirements

B.

Number of stakeholders that did not participate in the requirements elicitation

C.

Cost of actually eliciting the requirements

D.

Changes that entered the scope throughout the requirements elicitation activities

Question 83

Zoe is the business analyst for her organization. She is currently prioritizing the requirements based on the implementation difficulty of the requirements to help with the solution planning.

Which of the following best describes the approach Zoe is taking with requirements prioritization?

Options:

A.

The requirements are categorized by type of work, and then ranked within each category of ease of implementation to difficulty of implementation.

B.

The requirements are ranked most difficult to easiest to implement.

C.

The requirements are ranked from easiest to hardest to implement.

D.

The requirements are categorized by the likelihood of management approving the requirements.

Question 84

Which of the following is a process of adding labor to a project to reduce the project duration?

Options:

A.

Forming

B.

Storming

C.

Rolling wave planning

D.

Crashing

Page: 21 / 37
Total 497 questions