Winter Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

Certified Business Analysis Professional CBAP Updated Exam

Page: 17 / 37
Total 497 questions

Certified Business Analysis Professional Questions and Answers

Question 65

Henry is the business analyst for his organization and is completing the conduct elicitation activity. Part of this activity is to record the results of the requirements elicitation process.

All of the following are acceptable elements for requirements documentation except for which one?

Options:

A.

Text message sent via a secured mobile phone

B.

Written documents describing the outcomes

C.

Visual or audio recordings

D.

Whiteboards

Question 66

Your organization is using a plan-driven approach to business analysis.

What must you do with all of the communication documents created as part of this high-priority project that you are serving as the business analyst for?

Options:

A.

All formal communication must be destroyed once the project is completed.

B.

All communications must be documented and passed onto the solution's project manager for analysis and to serve as supporting detail.

C.

The communications management plan will dictate what will happen to the business analysis communications.

D.

All communications must be archived and will become part of the organizational process as sets.

Question 67

Which of the following is mandatory in most software development projects?

Options:

A.

Communication Management plan

B.

Disaster recovery plan

C.

Test plan

D.

Procurement plan

Question 68

You are the business analyst for your organization and you are preparing to elicit the requirements for a new business opportunity.

Which one of the following statements best describes the prepare for elicitation process?

Options:

A.

You need authority granted to you from the sponsor to utilize resources for the elicit requirements process.

B.

You need to determine which elicitation techniques are needed for the requirements gathering technique.

C.

You need to ensure all needed resources are organized and scheduled for conducting the elicitation activities.

D.

You need to receive permission from functional management to interview and elicit requirements for the stakeholders.

Page: 17 / 37
Total 497 questions