Question 137

Company A has been engaged to provided solution software to Company B as part of a combined service offering to Company C.

The initiative requires a sub project for Companies A and B learn Company Cs statutory requirements, a sub project for Company A to write custom functionality for the solution, and a sub project for Company B to develop infrastructure and support for the solution as well as the main project of implementation and cutover from Company Cs current data processing solution to the service from Company B, How does the business analyst (BA) assign requirements to the various solution components to ensure all objectives are met?

Options:

A.

Described Design Options

B.

Allocate Requirements

C.

Identify Improvement Opportunities

D.

Define Solution Approaches

Question 138

During the testing phase, a new requirement surfaced and the stakeholder asked the developer to modify the code without informing the Business analyst (BA). The BA became aware of the new functionality after a defect was raised against another component of the design. The BA can keep this situation from occurring in the future by creating a:

Options:

A.

risk strategy.

B.

prioritization approach.

C.

change control process.

D.

stakeholder engagement plan.

Question 139

While working on a major project to replace the billing mechanism at a bank, a major change in scope is discussed. Which approach does the business analyst (BA) use to help determine the formality of the assessment process to be followed to understand the impacts of the scope change?

Options:

A.

Governance

B.

Information management

C.

Stakeholder engagement

D.

Solution

Question 140

A business analyst (BA) has defined a business analysis approach and presented the documents to the sponsors, the senior executives, the domain experts, the project manager and the head of technology, to obtain agreement from all. At this juncture, the prefect manager objected to some of the estimates determined m the budget and refused to agree with the estimates. Which guideline or tool, if followed by the BA. would have helped in avoiding such disagreements?

Options:

A.

Requirements Classification Schema

B.

Stakeholder Engagement Approach

C.

Risk Analysis and Management

D.

Business Analysis Performance Assessment