Question 41

What document allows a LEED AP to register a project and sign the Certification Agreement?

Options:

A.

Owner Confirmation of Agent Authority

B.

Architect Code of Professional Conduct

C.

Commissioning (Cx) Agent Construction Permit

D.

LEED AP Standard Form of Agreement Between Owner and Architect

Question 42

What type of space should a project team ensure is made available in order to attain the Sustainable Sites Credit, Joint Use of Facilities, Option 1: Make Building Space Open to the General Public?

Options:

A.

Locker rooms

B.

Office of the principal

C.

Health clinic

D.

Auditorium

Question 43

How can the additional energy needed to increase the ventilation in a building be mitigated?

Options:

A.

Use economizer strategies

B.

Use higher-rated MERV filters

C.

Use high-pressure drop filters

D.

Reduce the size of the ventilation ductwork

Question 44

A LEED Building Design and Construction project includes an outdoor stage for theatrical performances. In pursuit of Sustainable Sites Credit, Light Pollution Reduction the engineer has specified an LED fixture to illuminate actors on the stage while limiting light pollution. Which of the following suggestions should the LEED AP give to the project owner?

Options:

A.

Modify the design to enclose the performance areas

B.

Calculate the return on investment over the 20-year life of the project

C.

Compare the energy consumption against an alternative

D.

Inform the owner that the LED fixture is exempt from Sustainable Sites Credit, Light Pollution Reduction