Question 69

The project team achieved a strategy not addressed in the LEED Green Building Rating System, which proved to be a significant, measurable environmental benefit for the project. What can the project team do in order to get a benefit for this strategy?

Options:

A.

Submit a regional priority credit

B.

No benefit can be achieved since the strategy is not included in the rating system

C.

Submit the manufacturer's product declaration

D.

Submit an innovation credit

Question 70

A new building containing private offices is pursuing Location and Transportation Credit, Access to Quality Transit. Which would comply?

Options:

A.

Locate the project ¼ mile (0.4 km) walking distance from two campus bus system lines (only accessible to campus students) with two stops each

B.

Locate the project ½ mile (0.8 km) walking distance from two bus lines with two stops each

C.

Locate the project ¼ mile (0.4 km) walking distance from a planned, funded, and partially complete subway station

D.

Locate the project ½ mile (0.8 km) walking distance from a planned, not funded commuter rail

Question 71

What are the Storage and Collection of Recyclables requirements for only Retail projects under the Materials and Resources Prerequisite?

Options:

A.

Retail projects must conduct a waste stream audit for the duration of the project in an existing location or make projections based on historical data for similar establishments. Identify the top-five recyclable waste streams while stating the top-four waste streams where both collection and storage space will be provided

B.

Retail projects must conduct a waste stream audit once a month for the project in an existing or rented location or make projections based on data gathered from a previous cycle. Identify the top-three recyclable waste streams while stating the top-two waste streams where both collection and storage space will be provided

C.

Retail projects must conduct a waste stream audit twice a year for the project in an existing or rented location or make projections based on the previous year's data for their business. Identify the top-four recyclable waste streams while stating the top-three waste streams where both collection and storage space will be provided

D.

Retail projects must conduct a waste stream audit for the once a year for the project in an existing or rented location or make projections based on the previous year's data for their business. Identify the top-four recyclable waste streams while stating the top-three waste streams where both collection and storage space will be provided

Question 72

Which of the following is required when documenting a LEED Pilot credit?

Options:

A.

Compliance letter

B.

LEED AP approval

C.

Innovation narrative

D.

Pilot Credit registration

Page: 18 / 25