Planning & Scheduling Professional (PSP) Exam Questions and Answers

Question 5

Assuming conventional finish-to-start relationships, to calculate a schedule retaining the existing logic means that

Options:

A.

It is calculated using the original logic.

B.

It is calculated using logic reflecting out-of-sequence progress.

C.

An out-of-sequence activity cannot resume until all predecessors are finished.

D.

There is no such thing.

Question 6

What does the heavy, vertical line at "X" represent?

Options:

A.

Delay fault line.

B.

The status or data date.

C.

Change-over limits.

D.

International Date Line.

Question 7

Which is NOT an industry-recognized methodology for quantifying critical delay?

Options:

A.

Gantt Chart.

B.

Periodic Windows.

C.

Collapsed As-Built.

D.

Time Impact.

Question 8

At a minimum, periodic reporting must be done at what interval?

Options:

A.

Monthly.

B.

As requested by the project manager.

C.

As requested by the owner.

D.

As specified in the contract documents.