Planning & Scheduling Professional (PSP) Exam Questions and Answers

Question 17

If the administrative constraints for developing the precedence diagram, as provided in the contract documents, indicate that no individual construction activities shall have a longer duration of two months, how many activities in the "normal" schedule would be affected?

Options:

A.

12.

B.

14.

C.

13.

D.

Cannot be determined.

Question 18

If a cost estimate assumes that 240 hours will be expended on a given activity, and the projected crew size expected to perform that activity is 5 personnel working and 8-hour workday, what is the calculated duration for the activity?

Options:

A.

8 days

B.

6 days

C.

4 days

D.

5 days

Question 19

Which of the following parties is NOT a stakeholder of the Spring Highway project?

Options:

A.

ALPHA

B.

GOUGE

C.

BILCO

D.

DEVCO

Question 20

Determine the correct formula and date for the late finish for Activity 9004.

Options:

A.

LF of 10002 less 24 days

B.

LS of 9004 plus 72 days

C.

LF of 8001 plus 72 days

D.

LS of 10002 less lag of 7 days plus 1 day equaling 20 Nov 2023