Planning & Scheduling Professional (PSP) Exam Questions and Answers

Question 17

Using the normal schedule, given Activity 3001 and the relationship with Activity 4001. what is indicated?

Options:

A.

The activities are independent, with Activity 4001 starting 15 days earlier than the start

of Activity 5001

B.

These activities are partially concurrent, with Activity 4001 starting 15 days after the

start of Activity 3001

C.

These activities are sequential, with Activity 4001 starting 15 days earlier than the start of Activity 3001.

Question 18

If drafting of the product manual overruns its planned duration by 5 days, how many days may the manufacturing be delayed without affecting release of the product?

Options:

A.

15 days.

B.

10 days.

C.

0 days.

D.

5 days.

Question 19

Which of these letters, symbols or words best approximates the graphical shape of a project's cumulative BCWS?

Options:

A.

/

B.

Bell curve

C.

S

D.

_

Question 20

What problems can a soils engineer deal with on a project?

Options:

A.

Survey error.

B.

Hidden subsurface conditions.

C.

Archeological findings.

D.

Toxic soils.