Resource planning must take all of the following into account except for:
At the end of month one, did the delay to the parking structure foundation delay the project?
There is only enough room for a maximum of 4 cranes to be placed on-site. Assuming that a single crane can perform 35 lifts per day and that a column pour requires 60 lifts, what is the minimum number of tower cranes that should be used for the above described column pours?
The data date or status date of a schedule represents the: