Planning & Scheduling Professional (PSP) Exam Questions and Answers

Question 33

If a contractor has robust planning and scheduling processes, should those company processes supersede client contract specifications?

Options:

A.

Proceed with company processes even if they conflict with the client

B.

The client contract specifications always have priority

C.

Review any differences and negotiate workable specifications

D.

Suggest that the client issue a change order, accepting the contractor's processes

Question 34

Due to a testing delay, release of the product for manufacture is delayed by 5 workdays and the product manual misses its print window at the printer. If the printer is delayed by 10 workdays, what is the delay to produce release?

Options:

A.

15 days.

B.

0 days.

C.

5 days.

D.

10 days.

Question 35

What is the actual duration as of the status date or data date of Activity B?

Options:

A.

7.

B.

3.

C.

0.

D.

4.

Question 36

Using one crane capable of 30 lifts per day. for 3 column pours requiring 28 lifts each, plus assorted work in the area requiring an additional 150 lifts, what are the lowest planned workdays for this work?

Options:

A.

3 workdays

B.

18 workdays

C.

8 workdays

D.

7 workdays