New Year Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

ASIS Physical Security Professional PSP New Questions

Page: 10 / 12
Total 163 questions

Planning & Scheduling Professional (PSP) Exam Questions and Answers

Question 37

SUBCO is a potential concrete bridge contractor based in a metropolitan area 300 miles away from your project. They have offered to supply manpower and equipment t BILCO at a per diem rate of $3,000 above their direct labor and equipment rates. In doing a cost benefit analysis, which of the following is NOT a consideration?

Options:

A.

SUBCO direct labor and equipment rates

B.

BILCO liquidated damages in the SDOT contract

C.

Pending negotiations with GOUGE.

D.

The distance of SUBCO to your project

Question 38

For activity 11001. why would the crashed direct cost be greater than the direct cost of the normal schedule?

Options:

A.

Additional extended overhead is also being shown in this activity

B.

Some costs resulting from the crashed efforts were forgotten in previous activities

C.

Generally, more equipment is used for a crashed project; therefore, it costs more to demobilize

D.

Management bonuses for early completion were included in this activity

Question 39

Which of the following is NOT true?

Options:

A.

Remaining durations can exceed original durations.

B.

Constraints can interfere with the longest path calculation.

C.

Multiple calendars can affect the total float calculation.

D.

A network must contain only one Critical Path.

Question 40

Determine the correct formula and date for the late start for Activity 9001.

Options:

A.

The early finish is required in order to determine the answer.

B.

LS.6001 Dur.6001 -> 11-20-02.

C.

There is insufficient data provided to calculate the answer.

D.

LF.9001 Dur.9001 -> 11-20-02.

Page: 10 / 12
Total 163 questions