Which of the following is NOT required when performing weekly or monthly schedule updates?
At the end of month one, did the delay to the parking structure foundation delay the project?
You are the project manager of the AHQ project. This project is scheduled to last for six months and will require S345.000 to complete. If the project completes earlier than scheduled your organization will receive a bonus of S5 000 per day of early completion Management has asked you to develop an aggressive schedule to realize as much of the bonus as possible but management does not want you to increase the costs of the project beyond $1,000 per day of the bonus realization. Which of the following approaches will likely add costs to the project?
What method would be the best way to determine the most likely as-built critical path of a project that is underway, and the schedule of which has been partially progressed?
Due to the delayed completion of Product Testing, the Release for Manufacture milestone was delayed by 5 workdays which thus delayed starting the Draft Product Manual activity. If the Print Product Manual activity is also delayed by 10 workdays, what is the delay to completing the Product Available milestone?
Determine the correct formula and date for the late start for Activity 9001.
Constructability is NOT intended to:
Using the crashed schedule, if you start Activity 2002 on 12 August 2021. what is the finish date for Activity 2002?
Project schedules help control all of the following EXCEPT for_____________________.
Assuming conventional finish-to-start relationships, to calculate a schedule retaining the existing logic means that
When are KPIs defined?
The sum of all budgets for work scheduled to be accomplished within a given time period is the ____________.
Determine the correct formula and date for the late finish for Activity 2002.
Why does activity 11001 not show successor activities?
Which of the following will NOT affect the total float calculation of a non-resource leveled schedule?
Which of the following project planning situations is the most frequent contributor to cost overruns?
Using the normal schedule, given Activity 3001 and the relationship with Activity 4001. what is indicated?
If drafting of the product manual overruns its planned duration by 5 days, how many days may the manufacturing be delayed without affecting release of the product?
Which of these letters, symbols or words best approximates the graphical shape of a project's cumulative BCWS?
What problems can a soils engineer deal with on a project?
The addition of which of the following relationships would cause a logic loop?
If a detailed estimate is NOT available to assist in the formulation of activity durations but unit quantities have been identified, what information can be utilized to estimate work package/activity durations?
When using a detailed estimate as the basis for work package/activity durations, which element does NOT need to be identified before the activity durations can be calculated?
Determine the correct formula and date for the late finish for Activity 9004.
Control Level Schedule activities are NOT one of the following:
What project cost elements would NOT normally be reflected in the Activity 1000?
What is a critical path method schedule?
All the following describe the critical path of a schedule EXCEPT:
Which of the following is not an internal stakeholder?
Scenario: You are providing construction management services for a small office building project. Your duties include reviewing and approving the contractor's baseline schedule. The contractor has submitted the first baseline schedule for the project.
The contractor's baseline schedule submittal includes a bar chart, but no CPM diagram. Which of the following is the most significant shortcoming to using a bar chart to review the baseline?
In order for a claimant to be entitled to an extension of contract time for a delay event (and further to be considered compensable):
What is the relationship depicted between Activity G and Activity H?
If a contractor has robust planning and scheduling processes, should those company processes supersede client contract specifications?
Due to a testing delay, release of the product for manufacture is delayed by 5 workdays and the product manual misses its print window at the printer. If the printer is delayed by 10 workdays, what is the delay to produce release?
What is the actual duration as of the status date or data date of Activity B?
Using one crane capable of 30 lifts per day. for 3 column pours requiring 28 lifts each, plus assorted work in the area requiring an additional 150 lifts, what are the lowest planned workdays for this work?
Which statement is true?
You are retained by a contractor who asks you to perform a simple as-planned versus as-built analysis (APAB) of a large hydro-electric dam project that took more than five years to complete. Your analysis will form the basis of a change order that requests a time extension. You suggest using a different methodology for quantifying the delay. Which of the following reasons for recommending a different analysis does NOT apply to a simple APAB analysis?
Activity 2003 started during the current reporting period and proceeded as planned with the normal schedule. If the remaining duration at the end of this period is ten workdays, then what is the earned value assignable to Activity 2003 in the pay estimate for this reporting period?
Prior to the start of work, Management determined the need to make the Product available 10 workdays earlier than planned. Which activities need to be expedited?
The Organizational Breakdown Structure (OBS) is a hierarchical structure that does NOT include which of the following:
The EBS is established by:
What does the narrow band at "Y" represent?
What does the narrow band at "Y" represent?
Should activities be coded with the EBS value?
Which of the following is NOT a tool or technique used to perform scope planning?
Schedule forecasts are periodically conducted to project the project schedule performance at completion Which of the following situations would probably result in an incorrect forecast?
The BEST reason to use multiple calendars is to:
Which of the following is least likely to affect the criticality of resources in resource planning process?
Which of the following documents is most likely to be of the LEAST value to a planner/scheduler when planning a contractor's baseline critical path schedule for the construction of a large high-clearance bridge located very near an airport? The contractor has been awarded the contract.
Management has determined the need to release the product 20 days earlier than planned. What tasks need to be expedited?
An early start constraint dictates
Activity 1001 started on the scheduled date but has slipped 10 days. Activity 10002 will slip 35 days. All remaining activities retain their original duration. What is the revised completion date?
There is only enough room for a maximum of 4 cranes to be placed on-site. Assuming that a single crane can perform 35 lifts per day and that a column pour requires 60 lifts, what is the minimum number of tower cranes that should be used for the above described column pours?
Before the work begins, the contractor considers crashing the schedule. How much would the crashed general conditions have to be reduced to break even with the normal cost budget?
Based on the stated costs, what percentage of the total cost comes from the 2000 series of activities?
How many entities/subcontractors should a scheduled activity cover?
Activity durations are normally estimated in an intuitive and subjective way. All of the following will improve duration accuracy EXCEPT
What changes to logic would eliminate Activity B from the critical path?
Determine the correct formula and date for the late finish for Activity 9004.
Time-scaled logic diagrams are
Who will receive the most benefit from a master schedule of the Spring Highway project?
These are the activities on the critical path:
If the administrative constraints for developing the precedence diagram, as provided in the contract documents, indicate that no individual construction activities shall have a longer duration of two months, how many activities in the "normal" schedule would be affected?