Big Halloween Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

PSP Premium Exam Questions

Page: 6 / 16
Total 216 questions

Planning & Scheduling Professional (PSP) Exam Questions and Answers

Question 21

The addition of which of the following relationships would cause a logic loop?

Options:

A.

O H - D

B.

O C - J

C.

O F-I

D.

O l-C

Question 22

If a detailed estimate is NOT available to assist in the formulation of activity durations but unit quantities have been identified, what information can be utilized to estimate work package/activity durations?

Options:

A.

The Eichleay formula

B.

Historical production rates

C.

Time impact analysis

D.

Black-Scholes model

Question 23

When using a detailed estimate as the basis for work package/activity durations, which element does NOT need to be identified before the activity durations can be calculated?

Options:

A.

Projected crew size

B.

Estimated labor hours

C.

Hours in a standard work day

D.

Estimated cost

Question 24

Determine the correct formula and date for the late finish for Activity 9004.

Options:

A.

LF of 10002 less 24 days

B.

LS of 9004 plus 72 days

C.

LF of 8001 plus 72 days

D.

LS of 10002 less lag of 7 days plus 1 day equaling 20 Nov 2023

Page: 6 / 16
Total 216 questions