Planning & Scheduling Professional (PSP) Exam Questions and Answers

Question 13

When resource leveling craft labor for a critical path schedule, the scheduler

Options:

A.

Must consider breaks in continuity of work for subcontractors, thereby possibly incurring additional subcontractor mobilization and demobilization costs.

B.

Can depend on the results of the resource leveling operation to reflect a useful realignment of all schedule activities without 'further analysis.

C.

Need not consider its effects, as it is a theoretical concept with limited application to construction projects.

D.

Need only consider the non-union crafts persons.

Question 14

Assuming activities 2001 through 2004 comprise the same WBS element, construct a WBS summary activity for activities 2001 through 2004. Use the normal schedule, what is the cost of the activity?

Options:

A.

$289.000

B.

$321.000

C.

$193,000

D.

$327,000

Question 15

Which activity is drawn in the incorrect position?

Options:

A.

Activity G.

B.

Activity E.

C.

Activity C.

D.

Activity D.

Question 16

Determine the correct formula and date for the late finish for Activity 2002.

Options:

A.

LS.2003 - 1 day -> 11.06.01.

B.

LS.2003 - 1 day -> 10-06-01.

C.

LS.2003 + 1 day -> 10-07-01.

D.

LS.2003 - 1 day -> 10-05-01.