Planning & Scheduling Professional (PSP) Exam Questions and Answers

Question 13

Determine the correct formula and date for the late finish for Activity 2002.

Options:

A.

LS of 2003 less 1 day equaling to 06 Oct 2021

B.

LS of 2003 less 1 day equaling to 06 Nov 2021

C.

LS of 2003 plus 1 day equaling to 07 Oct 2021

D.

LS of 2003 less 1 day equaling to 05 Oct 2021

Question 14

Why does activity 11001 not show successor activities?

Options:

A.

The early finish and late finish are circular

B.

It is the penultimate work required for the project

C.

The scheduler forgot to add the successor activities

D.

It is the final activity for the required work for the project

Question 15

Which of the following will NOT affect the total float calculation of a non-resource leveled schedule?

Options:

A.

Multiple calendars.

B.

Start and finish constraints.

C.

Preferential logic.

D.

Front end loading.

Question 16

Which of the following project planning situations is the most frequent contributor to cost overruns?

Options:

A.

lack of detailed planning for operational start-up

B.

Insufficient planning for change management

C.

Inappropriate definition of work breakdown structure

D.

Inadequate definition of scope at the estimate (budget) stage