Planning & Scheduling Professional (PSP) Exam Questions and Answers
Question 25
Is activity 7001 pictured correctly in the precedence diagram?
Options:
A.
No, the total float is not shown correctly.
B.
Yes, except the early finish date is not shown.
C.
No, the start-to-start and finish-to-finish relationships are backwards.
D.
Yes, the duration is 48 days.
Answer:
D
Question 26
Which of the following statements is true?
Options:
A.
In the absence of contrary contractual language network float, as opposed to project float, there is a shared commodity between the owner and contractor
B.
In the absence of a contrary contractual language total float, as opposed to free float, there is a commodity belonging to the contractor
C.
In the absence of contrary contractual language total float, as opposed to tree float, there is a commodity belonging to the owner
D.
In the absence of contrary contractual language free float, as opposed to project float, there is not a shared commodity between the owner and the contractor
Answer:
A
Question 27
Determine the correct formula and date for the late start for the Activity 11001:
Options:
A.
LF of 11001 less 27 days plus 1 day equaling 14 Jan 2024
B.
LF of 1000 less 25 days equaling 16 Jan 2024
C.
LF of 11001 less duration of 11001 equaling 16 Jan 2024
D.
LF of 11001 less 25 days plus 1 day equaling 16 Jan 2024
Answer:
A
Question 28
How much Total Float does drafting the product manual have?