The Organizational Breakdown Structure (OBS) is a hierarchical structure that does NOT include which of the following:
subcontractors
stakeholders
sub-subcontractors
project director
The EBS is established by:
The contractor s planning and scheduling office
The government entity with the authority to approve/stop the work
The entity with the authority to fund and direct the enterprise
The contractors and subcontractors
What does the narrow band at "Y" represent?
Resource limitation period.
A rework period.
Activity inactivity.
You cannot tell with the information supplied.
Interpret the Narrow Band at "Y":
The narrow band at "Y" is located on a part of the schedule where activities have been delayed or slowed down.
Such delays typically indicate resource limitations (e.g., insufficient manpower or equipment).
Reasoning:
No evidence of rework or activity inactivity is explicitly shown in the diagram.
Resource limitations are common in network diagrams to explain such periods.
Cross-Verification:
Option B: Incorrect. No evidence of rework exists.
Option C: Incorrect. Activity inactivity does not fit the context.
Option D: Incorrect. Sufficient information is provided.
Option A: Correct. Resource limitation fits the observed diagram behavior.
Resource limitation period
A delaying event
You cannot tell with the information supplied
A rework period