Helping Hand Questions for PSP

Page: 11 / 12
Total 163 questions

Planning & Scheduling Professional (PSP) Exam Questions and Answers

Question 41

Scenario:

The entire network consists of the following activities and relationships. Activity A is twenty days long and is tied to Activity B, a ten-day activity, with a finish-to-finish tie with a lag value of five Activity B is tied to Activity C, a twenty-day activity, with a start-to-start relationship with a lag value of five.

PSP Activities Table

Scope Known about Rock-Filled Dam Project:

The dam requires river diversion and work over two or more rainy seasons. The contract is lump sum, competitively bid, and will be self-performed. The owner has attempted to shift all risk to the contractor by employing "no differing sit conditions" and "no damage for delay" clauses. There is a bonus/penalty provision of $2,500 per calendar day for early or late delivery. The early completion bonus is capped at $500,000, with no cap for late delivery penalty.

Liquidated damages end at the finish of demobilization. Indirect costs per calendar day are $2,800 for the "normal" schedule and $3,200 for the "crashed" schedule. The winter/wet weather season is 151 days between October 15 and March 25 of each year, reduces the efficiency of the contractor's operations by 20% and costs the contractor $10,000 per day. Assume a start date of March 5, 2001 and use a 7-day work week.

The following table lists work activities as planned by the contractor.

Theoretically construct a summary activity for only those activities with a finish-to-start relationship for Activities 8001 through 10001. Using the "normal" schedule, what is the cost of this hammock?

Options:

A.

$420,000.

B.

$307,000.

C.

$524,000.

D.

$552,000.

Question 42

Using the normal schedule and excluding general conditions, which activities are NOT on the critical path?

Options:

A.

6001, 8001, 9001. 9002, 9004. 9005

B.

7001, 8001, 9001. 9003. 9004. 10002

C.

5001,7001.8001,9001,9004,9005

D.

2003,8001.9001.9002,9005,10001

Question 43

As a change to the network for the current update, activity 6002 is required to begin ten days after the beginning of activity 6001. Which is the simplest logic organization?

Options:

A.

A start-to-start relationship with a ten-day lag assigned to activity 6001; activity 6002 will be dependent on activity 6001

B.

A start-to-start to relationship for both activities 6001 and 6002 with a ten-day lag assigned to activity 6002.

C.

A start-to-finish relationship with both activities 6001 and 6002 having a ten-day lag

D.

A finish-to-start relationship with a ten-day lag assigned to activity 6002; activity 6001 will be dependent on activity 6002

Question 44

Assuming a total of 30 lifts per crane per day, what is the maximum number of lifts that could be accomplished using 3 small tower cranes over a 5-day period?

Options:

A.

450 lifts

B.

300 lifts

C.

45 lifts

D.

150 lifts