New Year Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Physical Security Professional PSP Release Date

Page: 8 / 12
Total 163 questions

Planning & Scheduling Professional (PSP) Exam Questions and Answers

Question 29

When using a detailed estimate as the basis for work package/activity durations, which element does NOT need to be identified before the activity durations can be calculated?

Options:

A.

Projected crew size

B.

Estimated labor hours

C.

Hours in a standard work day

D.

Estimated cost

Question 30

In a "crashed" schedule, which is a chain of activities that precede activity 2004?

Options:

A.

1001, 2001, 2002, 2003

B.

2001, 2002, 2003, 2007

C.

1001, 2002, 2003

D.

1001, 2002, 2002, 2003, 3001

Question 31

What day would Activity C complete if the duration of Activity B was reduced to zero?

Options:

A.

50

B.

20

C.

30

D.

40

Question 32

These are the activities on the critical path:

Options:

A.

A, D, & I.

B.

A, C, E, & H.

C.

A, B, G, & H.

D.

A, B, F, & J

Page: 8 / 12
Total 163 questions