Planning & Scheduling Professional (PSP) Exam Questions and Answers

Question 29

Which of the following is not an internal stakeholder?

Options:

A.

Owner

B.

installer

C.

Subcontractor

D.

Prime Contractor

Question 30

Scenario: You are providing construction management services for a small office building project. Your duties include reviewing and approving the contractor's baseline schedule. The contractor has submitted the first baseline schedule for the project.

The contractor's baseline schedule submittal includes a bar chart, but no CPM diagram. Which of the following is the most significant shortcoming to using a bar chart to review the baseline?

Options:

A.

A bar chart cannot accurately reflect the impact of changes in durations or logic to the baseline

B.

A bar chart is always an oversimplified view of the project schedule

C.

A tor chart does not show all the activities required to construct the project

D.

A bar chart does not show whether the project with be completed within the allowable time

Question 31

In order for a claimant to be entitled to an extension of contract time for a delay event (and further to be considered compensable):

Options:

A.

The delay must affect the critical path.

B.

The delay must be concurrent with the delay attributable to both parties.

C.

The delay must not cause monetary harm to the defendant.

D.

The delay must affect the contractor's planned construction schedule.

Question 32

What is the relationship depicted between Activity G and Activity H?

Options:

A.

You cannot tell with the supplied information.

B.

Start-to-start.

C.

Finish-to-start.

D.

Finish-to-finish.