A project change is approved by the Change Control Board that modifies the project scope. Which of the following is the NEXT step that the project manager should take?
The amount of time ahead or behind schedule on a project is called the:
A project manager has to complete an asset inventory project for a large corporation. Several departments have refused to allow access to the equipment to complete the project. The project manager should update which of the following?
A project manager is performing activity duration estimation for a project. Using expert judgment the project manager has three values for each activity: the worst case, most likely case, and best case. Which of the following tools would be the BEST to use?