Question 33

Which of the following would a project manager do NEXT after selecting a vendor for a project?

Options:

A.

Determine a list of qualified sellers.

B.

Determine vendor resource availability.

C.

Hold a bidders conference.

D.

Negotiate the contract.

Question 34

During execution, a project manager of a construction project requires certain project team members to work outdoors, atop tall buildings. Which of the following would BEST mitigate the risk of injury to those team members, without affecting the approved project schedule?

Options:

A.

Ensure that project team members do not work in very windy weather.

B.

Ensure that project team members are furnished with slip-resistant boots.

C.

Ensure that project team members are trained in injury response.

D.

Ensure that project team members are covered by applicable insurance.

Question 35

A project manager is implementing a new community park and wants to build public support. Which of the following communication mediums would BEST facilitate the goal?

Options:

A.

Send a personally signed letter to the residents.

B.

Hold a public ceremony at the location for the residents.

C.

Hold a teleconference for residents.

D.

Send an email to the community residents.

Question 36

The project team has completed phase testing. After testing, a subject matter expert (SME) notices that a component was skipped.

Which of the following should the project manager do?

Options:

A.

Proceed with the release and document the adjustment in the change log.

B.

Proceed with the release and tell the SME the component will be added in a special release.

C.

Delay the release until the component is tested.

D.

Schedule a meeting with the stakeholders to review the impact.