New Year Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Exactprep JK0-017 Questions

Page: 3 / 15
Total 402 questions

CompTIA E2C Project+ Certification Exam Questions and Answers

Question 9

In working with the risk management plan all of the following are ways of dealing with opportunities EXCEPT:

Options:

A.

exploiting.

B.

mitigating.

C.

sharing.

D.

enhancing.

Question 10

The project kick-off meeting is held:

Options:

A.

at the end of the planning process.

B.

before getting a signed project charter.

C.

during the initiating process.

D.

after the post review meeting.

Question 11

A project manager is analyzing the network schedule to determine the early start and early finish dates as well as the late start and late finish dates, for each activity. The project manager is not taking into account any resource constraints. Which of the following methods is demonstrated in this scenario?

Options:

A.

Critical Chain Method (CCM)

B.

Precedence Diagramming Method (PDM)

C.

Arrow Diagramming Method (ADM)

D.

Critical Path Method (CPM)

Question 12

There are three teams assigned to the same project. Two of the project teams are ahead of schedule; however, the product does not meet the needed quality standards. The third project team is behind schedule, but their product meets the quality standards. Which of the following should be the NEXT step for the project manager?

Options:

A.

Inform the stakeholders that the project is behind schedule.

B.

Meet with the teams to clarify the schedule and the quality standards expected.

C.

Crash the schedule to meet the project timeline.

D.

Fast track the schedule to complete the project on time without impacting the quality of the product.

Page: 3 / 15
Total 402 questions