In working with the risk management plan all of the following are ways of dealing with opportunities EXCEPT:
The project kick-off meeting is held:
A project manager is analyzing the network schedule to determine the early start and early finish dates as well as the late start and late finish dates, for each activity. The project manager is not taking into account any resource constraints. Which of the following methods is demonstrated in this scenario?
There are three teams assigned to the same project. Two of the project teams are ahead of schedule; however, the product does not meet the needed quality standards. The third project team is behind schedule, but their product meets the quality standards. Which of the following should be the NEXT step for the project manager?