Project+ JK0-017 Release Date

Page: 13 / 15
Total 402 questions

CompTIA E2C Project+ Certification Exam Questions and Answers

Question 49

All of the following occur during the project closure phase EXCEPT:

Options:

A.

ensure the project is aligned with organizational goals.

B.

ensure document retention compliance is being performed.

C.

release project team resources.

D.

close contracts and pay vendors.

Question 50

A project manager was asked to complete a project three weeks early and not crash the project. Which of the following should be done?

Options:

A.

Move some of the task to another release.

B.

Have the team work over time and give them time off later to save the budget.

C.

Continue to work and complete the project as soon as possible.

D.

Review the plan with the team and develop a way to reduce the time

Question 51

In which of the following organization types would a project manager have the LEAST amount of project authority?

Options:

A.

Functional

B.

Strong Matrix

C.

Balanced Matrix

D.

Weak Matrix

Question 52

Which of the following shows a project that is presently over its financial budget?

Options:

A.

CPI = 1.4

B.

CPI = 0

C.

CV = +$11,000

D.

CPI = 0.8

Page: 13 / 15