CompTIA Project+ JK0-017 New Questions

Page: 8 / 15
Total 402 questions

CompTIA E2C Project+ Certification Exam Questions and Answers

Question 29

Which of the following may require a modification to the project scope baseline?

Options:

A.

An approved project change request

B.

A team member removed from the project

C.

A task that is falling behind schedule

D.

An identified product quality issue

Question 30

A project has been cancelled during the execution phase. Which of the following steps should be taken?

Options:

A.

Continue to work the project.

B.

Finish the project charter and project plan.

C.

Complete lessons learned document.

D.

Develop the project transition plan.

Question 31

A project is cancelled unexpectedly prior to completion. Which of the following would the project manager use to document the details of the project closure?

Options:

A.

Histogram

B.

Post mortem

C.

SWOT analysis

D.

Project scope statement

Question 32

Which of the following is the BEST reason to review the historical information from a similar project?

Options:

A.

To get a good idea of the writing style of the project manager.

B.

To get an understanding of the number of managers within the organization.

C.

To get an understanding of the resources needed to complete the project.

D.

To get an understanding of the document approval process.

Page: 8 / 15
Total 402 questions