Question 37

The initiation process concludes with the creation of which of the following?

Options:

A.

Contingency reserve

B.

Project charter

C.

Project schedule

D.

Project scope statement

Question 38

Information regarding training, extended support, and warranties are detailed in the:

Options:

A.

Risk register

B.

Project scope statement

C.

Work breakdown structure (WBS)

D.

Transition plan

Question 39

During final inspection, a project team member finds a deficiency in the product. In which of the following did this action occur?

Options:

A.

Gap analysis

B.

Quality control

C.

Process audit

D.

Quality assurance

Question 40

The project manager has the MOST authority in which of the following organizational structures?

Options:

A.

Balanced Matrix

B.

Functional

C.

Weak Matrix

D.

Strong Matrix