An experienced team member comes to the project manager to report that they are uncertain of the project requirements. This can MOST likely be attributed to:
Which of the following are components of an internal / external communication plan? (Select Two).
A project has been delayed due to an ongoing labor dispute. The project sponsor asks the project manager to transfer the risk to complete the project on time. Which of the following is a method of transferring the risk?
A project manager is working with a large team on an important project. Many of the team members work remotely. The project manager requires each team member to submit weekly status reports at a certain time each week. One team member consistently submits late status reports. Which of the following should the project manager consider FIRST?
A project change is approved by the Change Control Board that modifies the project scope. Which of the following is the NEXT step that the project manager should take?
The amount of time ahead or behind schedule on a project is called the:
A project manager has to complete an asset inventory project for a large corporation. Several departments have refused to allow access to the equipment to complete the project. The project manager should update which of the following?
A project manager is performing activity duration estimation for a project. Using expert judgment the project manager has three values for each activity: the worst case, most likely case, and best case. Which of the following tools would be the BEST to use?
In working with the risk management plan all of the following are ways of dealing with opportunities EXCEPT:
The project kick-off meeting is held:
A project manager is analyzing the network schedule to determine the early start and early finish dates as well as the late start and late finish dates, for each activity. The project manager is not taking into account any resource constraints. Which of the following methods is demonstrated in this scenario?
There are three teams assigned to the same project. Two of the project teams are ahead of schedule; however, the product does not meet the needed quality standards. The third project team is behind schedule, but their product meets the quality standards. Which of the following should be the NEXT step for the project manager?
Which of the following would require that the project risk register be updated?
Which of the following sequences represents the correct order for implementing a change request?
A project manager is managing a project that is scheduled to take ten months to complete. The project is in its sixth month and $450,000 has been spent. The project budget is $990,000. Which of the following will the project manager use to determine the budgeted cost of work scheduled?
Which of the following resource leveling techniques describes schedule compression by performing activities concurrently?
Who has the MOST control over project scope changes?
If the EV is $3,000 and the AC is $4,000, which of the following is the CV for the project?
Which of the following is an important aspect of formal project closure?
Which of the following are examples of a good business case for a new project? (Select Two).
During the execution of an assigned task the developer informs the project manager of a missing component. Which of the following should the project manager do next?
Which of the following is an input to a work breakdown structure (WBS)?
Which of the following would be contained in the problem statement within the project charter?
A project manager needs to replace someone on the project team. Which of the following is the FIRST action they should take?
Which of the following is a tool that can be used to identify project team members that are responsible for a task or deliverable?
Which of the following documents should be used to present the length of identified tasks?
The project scope document should outline which of the following project items? (Select Two).
When would a project manager have a closure meeting? (Select Three).
Which of the following may require a modification to the project scope baseline?
A project has been cancelled during the execution phase. Which of the following steps should be taken?
A project is cancelled unexpectedly prior to completion. Which of the following would the project manager use to document the details of the project closure?
Which of the following is the BEST reason to review the historical information from a similar project?
Which of the following would a project manager do NEXT after selecting a vendor for a project?
During execution, a project manager of a construction project requires certain project team members to work outdoors, atop tall buildings. Which of the following would BEST mitigate the risk of injury to those team members, without affecting the approved project schedule?
A project manager is implementing a new community park and wants to build public support. Which of the following communication mediums would BEST facilitate the goal?
The project team has completed phase testing. After testing, a subject matter expert (SME) notices that a component was skipped.
Which of the following should the project manager do?
The initiation process concludes with the creation of which of the following?
Information regarding training, extended support, and warranties are detailed in the:
During final inspection, a project team member finds a deficiency in the product. In which of the following did this action occur?
The project manager has the MOST authority in which of the following organizational structures?
Which of the following is the BEST report to provide to senior management?
A team member on a project uncovers a minor risk with the quality of a purchased component. The team uses their combined expert judgment to determine that the risk to the deliverable is very low. Which of the following is the MOST likely action the project manager should take?
A project manager is managing the delivery of a project awarded under a fixed-cost contract. The project cost was poorly planned and underestimated, but the projects overall scope and deadline cannot change. Failure to deliver the project is not an option. Which of the following will MOST likely be affected by these circumstances?
Who has the MOST control over project scope changes?
Who should conduct lessons learned when an outside vendor is used?
Which of the following is the purpose of a Pareto diagram?
Which of the following tools are used for quality planning? (Select Two).
Which of the following are created using information contained in the work breakdown structure (WBS)? (Select Two).
All of the following occur during the project closure phase EXCEPT:
A project manager was asked to complete a project three weeks early and not crash the project. Which of the following should be done?
In which of the following organization types would a project manager have the LEAST amount of project authority?
Which of the following shows a project that is presently over its financial budget?
A major change has been approved by the change control board and it now needs to be scheduled for implementation. Which of the following is the BEST method of implementing the change?
A project manager is reviewing the ownership, date, and the necessary training for a deliverable. Which of the following documents would include this information?
Which of the following components are included in a communication plan? (Select Two).
A stakeholder has determined the need to update their payroll method with a new system. Which of the following is the FIRST activity the corporation should perform?
Which of the following occurs during a project kick-off meeting? (Select Two).
Which of the following is a use for a Pareto diagram?
In which of the following organization types would a project manager have the MOST authority?
Which of the following risk response strategies involves shifting the negative impact of a threat, along with ownership of the response, to a third party?