New Year Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Project+ JK0-017 Passing Score

Page: 4 / 15
Total 402 questions

CompTIA E2C Project+ Certification Exam Questions and Answers

Question 13

Which of the following would require that the project risk register be updated?

Options:

A.

A qualitative risk analysis is performed

B.

A stakeholder has concerns about material delays

C.

The risk management plan is created

D.

Increased costs for required materials

Question 14

Which of the following sequences represents the correct order for implementing a change request?

Options:

A.

Change is requested, change impact analyzed, change request submitted to board, change request approved, change implemented.

B.

Change is requested, change implemented, change impact analyzed, change request submitted to board, change request approved.

C.

Change is requested, change request submitted to board, change impact analyzed, change request approved, change implemented.

D.

Change is requested, change request submitted to board, change request approved, change implemented, change impact analyzed.

Question 15

A project manager is managing a project that is scheduled to take ten months to complete. The project is in its sixth month and $450,000 has been spent. The project budget is $990,000. Which of the following will the project manager use to determine the budgeted cost of work scheduled?

Options:

A.

Estimate to completion

B.

Planned value

C.

Cost performance index

D.

Budget at completion

Question 16

Which of the following resource leveling techniques describes schedule compression by performing activities concurrently?

Options:

A.

Exploiting

B.

Crashing

C.

Optimizing

D.

Fast tracking

Page: 4 / 15
Total 402 questions