New Year Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Vce JK0-017 Questions Latest

Page: 14 / 15
Total 402 questions

CompTIA E2C Project+ Certification Exam Questions and Answers

Question 53

A major change has been approved by the change control board and it now needs to be scheduled for implementation. Which of the following is the BEST method of implementing the change?

Options:

A.

Distribute details of the change per the communication plan, and implement according to the change control process.

B.

Ask the change control board to schedule the change, and when scheduled, identify the individual team member responsible for implementing it.

C.

Email the project team, identifying the team member responsible for implementing the change, and then schedule it with the appropriate team members.

D.

Identify the team member responsible for implementing the change and direct the team member to inform the rest of the project team of the date and time of implementation.

Question 54

A project manager is reviewing the ownership, date, and the necessary training for a deliverable. Which of the following documents would include this information?

Options:

A.

Transition plan

B.

Quality plan

C.

Change Control plan

D.

Procurement plan

Question 55

Which of the following components are included in a communication plan? (Select Two).

Options:

A.

Statement of Work (SOW)

B.

Risk matrix

C.

Frequency

D.

Work Breakdown Structure (WBS)

E.

Distribution list

Question 56

A stakeholder has determined the need to update their payroll method with a new system. Which of the following is the FIRST activity the corporation should perform?

Options:

A.

Conduct a feasibility study.

B.

Determine the justification of the project.

C.

Obtain a preliminary review by the project selection committee.

D.

Determine if the project is in alignment with the companys strategic plan.

Page: 14 / 15
Total 402 questions