New Year Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Download Full Version JK0-017 CompTIA Exam

Page: 11 / 15
Total 402 questions

CompTIA E2C Project+ Certification Exam Questions and Answers

Question 41

Which of the following is the BEST report to provide to senior management?

Options:

A.

Daily progress report

B.

Milestone report

C.

Quality audit

D.

Work performance report

Question 42

A team member on a project uncovers a minor risk with the quality of a purchased component. The team uses their combined expert judgment to determine that the risk to the deliverable is very low. Which of the following is the MOST likely action the project manager should take?

Options:

A.

Issue a change request to the change control board to select a different vendor from the qualified sellers list and request early termination of the current vendors contract.

B.

Call a project team meeting to discuss the risk and communicate the issue directly with the project sponsor.

C.

Contact the vendor and request a thorough review of the products architecture.

D.

Document the risk in the risk register, accept it and refer to the agreed vendor contracts for methods of raising the issue with the vendor.

Question 43

A project manager is managing the delivery of a project awarded under a fixed-cost contract. The project cost was poorly planned and underestimated, but the projects overall scope and deadline cannot change. Failure to deliver the project is not an option. Which of the following will MOST likely be affected by these circumstances?

Options:

A.

Earned Value (EV)

B.

Quality

C.

Change management

D.

Resource leveling

Question 44

Who has the MOST control over project scope changes?

Options:

A.

Key stakeholders

B.

Project sponsor

C.

Project manager

D.

Change control board

Page: 11 / 15
Total 402 questions