Winter Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

Vce PMI-RMP Questions Latest

Page: 14 / 16
Total 221 questions

PMI Risk Management Professional (PMI-RMP) Exam Questions and Answers

Question 53

A risk manager notices that a risk owner is facing challenges implementing their response strategy and the costs are significantly exceeding expectations. What is the first thing the risk manager should do?

Options:

A.

Highlight this situation to the project manager

B.

Conduct a cost-benefit analysis

C.

Change the risk response strategy

D.

Analyze the situation and meet with the risk owner

Question 54

.

A project manager is identifying risks on a project and decides to use a risk checklist to gather historical data accumulated from similar projects. With several different historical project files to choose from, which two pieces of information should the project manager include in their risk checklist? (Choose two.)

Options:

A.

Budget variance data from previously completed projects.

B.

Project scope and cost management plans from previous projects.

C.

Lessons learned from similar completed projects.

D.

Previous project risks that may be relevant to this project.

E.

Stakeholder analysis metrics from projects with similar risk profiles.

Question 55

The project risk manager on a large firm fixed priced (FFP) contract has an up-to-date risk register with accurate and detailed information. What should the project risk manager do next?

Options:

A.

Recommend the removal of risks to the project manager to reduce project risk exposure.

B.

Advise the client that the project has exhausted contingency.

C.

Quantify the risk exposure that exceeds project contingency.

D.

Generate reports to assess and communicate the project risk level.

Question 56

A certain risk is identified for a major project, and the risk response is planned. However, the analysis reveals a high probability for a secondary risk which will be tolerated based on the organization's risk thresholds. The secondary risk is subsequently registered. During project execution, the primary risk occurs, the planned action is taken, and the secondary risk emerges

What two actions should the risk owner take? (Choose two.)

Options:

A.

Implement the secondary risk response and update the project documents.

B.

Conduct meeting with all stakeholder to agree on post impact solutions.

C.

Set the corresponding trigger conditions to the secondary risk.

D.

Engage the project manager to authorize the secondary risk's response.

E.

Update and communicate assessments of the secondary risk's impact.

Page: 14 / 16
Total 221 questions