The project risk manager for an environmental preservation project has started the process of monitoring and controlling risks, The project manager has asked the project team to document the results of this process.
How should this documentation be utilized in the future?
A new risk manager has been assigned to a project experiencing delays, quality issues, low performance, and client complaints. The work is being completed with the
client's vendor, which apparently has been causing all of the issues.
What should the risk manager do first?
A subcontractor working on a project may cause delays in the construction schedule. The project manager records this risk in the risk register and issues a change request sponsor rejects the change request.
What should the project manager have done differently?
During a meeting to develop the risk management plan, the risk manager recognizes that risks may be identified that could also impact other projects that the company is pursuing. What should the risk manager do?