Winter Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

PMI-RMP PMI Exam Lab Questions

Page: 2 / 16
Total 221 questions

PMI Risk Management Professional (PMI-RMP) Exam Questions and Answers

Question 5

A project manager has requested the risk manager's support in deciding whether to purchase a new component to expedite project execution. The component price is US$100,000 and there is a 30% chance that it might not function as expected resulting in an additional US$50,000 cost However, if the component does work well the project will make a profit of USS500.000. If the component is not purchased, there is an 80% chance of failure with an impact of US$250 000.

What should the risk manager recommend?

Options:

A.

The new component should be purchased.

B.

Both options are losses to the project.

C.

Cost to expedite the execution is not worth the added risk.

D.

Perform a Monte Carlo simulation to quantify the impacts.

Question 6

A subcontractor working on a project may cause delays in the construction schedule. The project manager records this risk in the risk register and issues a change request sponsor rejects the change request.

What should the project manager have done differently?

Options:

A.

Executed the risk strategy response and recorded it in the risk register.

B.

Performed an analysis to affirm the request is valid before submitting.

C.

Informed the client and the project sponsor that the request is being submitted.

D.

Contacted the other stakeholders so they know the request is in process.

Question 7

Some project risks are applicable for the project's lifecycle while others risks are only applicable to specific project activities. When should project risks be closed?

Options:

A.

When the forecast activity date has been met or exceeded

B.

When the stakeholders agree a risk is no longer applicable

C.

When the risk has been realized and can no longer happen again

D.

When iterative data analysis determines the risk is not applicable

Question 8

While implementing the risk response plan for a previously identified risk, some secondary risks were identified but not captured on the risk register. The project manager decided to review the risk management plan to ensure this does not happen for future, similar situations.

What should the project manager do next?

Options:

A.

Identify secondary or residual risks for associated risk plans.

B.

Develop risk response plans for all identified risks.

C.

Update the communications management plan to avoid future issues

D.

Monitor and control secondary and residual risks in the risk register.

Page: 2 / 16
Total 221 questions