Winter Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

PMI-RMP VCE Exam Download

Page: 3 / 16
Total 221 questions

PMI Risk Management Professional (PMI-RMP) Exam Questions and Answers

Question 9

In a large mobile network deployment project, there is delay risk due to insufficient staffing. The risk manager is considering executing a response plan, which involves allowing staff members to work overtime. However, this action may lead to excessive additional cost.

What should the risk manager do?

Options:

A.

Document the concern over the potential excessive additional cost.

B.

Manage the potential excessive additional cost as a new risk.

C.

Ensure the project sponsor has the risk appetite for the residual risk created by allowing overtime.

D.

Prepare a detailed response plan for the residual risk with a clear owner and time line to ensure there are no impacts to the project.

 

Question 10

A risk manager manages risks in a construction project. A stakeholder mentions that if there is less than a 50% chance of rain, construction should continue. Another stakeholder says that if there is less than a 60% chance of rain, construction should continue.

What should the risk manager do next to find out the correct limit?

Options:

A.

Review the agreed-upon risk tolerance

B.

Perform a sensitivity analysis of the risk

C.

Find out the stakeholders’ risk appetite

D.

Use industry standard risk thresholds

Question 11

A project manager for a large product development project assigned a risk manager to perform the risk management. The project sponsor questions why this project requires a risk manager as it is similar to a previous project with a developed risk strategy.

How should the risk manager explain the need for a risk strategy specific to this project?

Options:

A.

A risk strategy is a best practice and ensures quality in the project planning.

B.

A project specific risk strategy includes enough information to respond to audits and compliance requirements.

C.

A risk strategy ensures alignment of the organizational structure to the specific project.

D.

A risk strategy aligns individual project risk thresholds with organizational risk appetite.

 

Question 12

A project team has completed the risk response plan for a newly identified major project risk. Some team members argue the plan does not totally eliminate the risk, considering the effort required to implement it, and feel the planned response should be thrown out altogether.

What should the risk manager do in this situation?

Options:

A.

Accept the response because there are no secondary risks were identified.

B.

The response plan should be discontinued and the risk should be accepted and dealt with if it occurs.

C.

Accept the residual risk as it is compatible with the organization's risk appetite.

D.

All identified risks must be addressed because they might significantly impact the project if they occur.

 

Page: 3 / 16
Total 221 questions