Summer Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

PMI-RMP VCE Exam Download

Page: 3 / 20
Total 264 questions

PMI Risk Management Professional (PMI-RMP) Exam Questions and Answers

Question 9

An IT project is 40% complete. During the initial analysis, risks A and B were identified for the project. Risk A has a probability of 0.6 and an impact of US$50.000. Risk B has a probability of 0.7 and an impact of USS60.000. After implementing the planned risk response for risk B. the probability of risk B has been reduced is 0.3.

What is the current project risk exposure?

Options:

A.

US$18,000

B.

US$72.000

C.

US$30,000

D.

US$48,000

Question 10

A project manager has been assigned to a project that is just starting. The organization has a very low risk appetite towards this project due to constraints on budget and schedule. The project stakeholders are very engaged on the project and want to ensure that there is clear visibility on the project risks and progress.

How should the project manager handle stakeholder expectations?

Options:

A.

Add buffers to the schedule to accommodate risk.

B.

Ensure the risk register includes all identified risks.

C.

Discuss the risk response strategies with the stakeholders.

D.

Develop a communication plan to share updates on risks.

Question 11

A risk manager documents the causes in the risk register and needs to ensure the risk is adequately described. What is critical for the risk manager to consider when describing the causes?

Options:

A.

Each cause has a degree of uncertainty

B.

Each cause has well defined owner

C.

The causes represent actual conditions

D.

The causes must be validated by the risk owner

Question 12

After presenting a list of risks to the major project stakeholders and project sponsor, the board requested the risks be sorted differently from the results presented by the project team. This is a major issue and will cause a 2-week delay in the project.

How could the risk manager have avoided the board's response?

Options:

A.

Engaging the key stakeholders during the prioritization process

B.

Prioritizing the risks based on the project sponsor's risk appetite

C.

Engaging with the project sponsor before presenting to the board

D.

Working with an established industry standard prioritization method

Page: 3 / 20
Total 264 questions