New Year Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Free PMI-RMP PMI Updates

Page: 4 / 10
Total 131 questions

PMI Risk Management Professional (PMI-RMP) Exam Questions and Answers

Question 13

The project sponsor asks the project manager about the accuracy of the project data. The project manager realizes that some risks have not been updated recently.

What should the project manager do regarding those risks?

Options:

A.

Review the assumptions analysts

B.

Conduct a checklist analysis on each risk

C.

Create a risk response plan for those risks

D.

Review the risk register to check for the new risks

Question 14

A complex project that had hundreds of risks is almost done. The project manager is closing the risks as part of the closing process. One team member mentions that there are important documents to be updated.

Which document will need to be updated?

Options:

A.

Lessons learned

B.

Contingency register

C.

Risk register

D.

Issue log

Question 15

Several key stakeholders approach the project manager with concerns. The stakeholders have received feedback from local businesses that have reported a reduction in customers because of construction activities at the worksite, and they plan to submit a claim to the municipality to fine the project manager's company.

How should the project manager address this concern?

Options:

A.

Evaluate the risk with the team and update the issueing

B.

Discuss the concern with the local business owners.

C.

Update the key risks and perform a quantitative risk analysis.

D.

Adjust construction work hours to after business hours.

Question 16

A project manager wants to work on understanding the project risks. The project manager works with the integrated project team to develop the risk handling strategies for the identified risks.

How should the project manager work with these risk handling strategies?

Options:

A.

Review and revise the strategies periodically.

B.

Implement the strategies after completing the risk analysis.

C.

Implement the strategies immediately.

D.

Ensure the strategies are approved by the stakeholders.

Page: 4 / 10
Total 131 questions