New Year Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

PMI-RMP Exam Dumps : PMI Risk Management Professional (PMI-RMP) Exam

PDF
PMI-RMP pdf
 Real Exam Questions and Answer
 Last Update: Dec 21, 2024
 Question and Answers: 131 With Explanation
 Compatible with all Devices
 Printable Format
 100% Pass Guaranteed
$25.5  $84.99
PMI-RMP exam
PDF + Testing Engine
PMI-RMP PDF + engine
 Both PDF & Practice Software
 Last Update: Dec 21, 2024
 Question and Answers: 131
 Discount Offer
 Download Free Demo
 24/7 Customer Support
$40.5  $134.99
Testing Engine
PMI-RMP Engine
 Desktop Based Application
 Last Update: Dec 21, 2024
 Question and Answers: 131
 Create Multiple Test Sets
 Questions Regularly Updated
  90 Days Free Updates
  Windows and Mac Compatible
$30  $99.99

Verified By IT Certified Experts

CertsTopics.com Certified Safe Files

Up-To-Date Exam Study Material

99.5% High Success Pass Rate

100% Accurate Answers

Instant Downloads

Exam Questions And Answers PDF

Try Demo Before You Buy

Certification Exams with Helpful Questions And Answers

PMI Risk Management Professional (PMI-RMP) Exam Questions and Answers

Question 1

A complex project that had hundreds of risks is almost done. The project manager is closing the risks as part of the closing process. One team member mentions that there are important documents to be updated.

Which document will need to be updated?

Options:

A.

Lessons learned

B.

Contingency register

C.

Risk register

D.

Issue log

Buy Now
Question 2

A mega facility development project is evaluating some options to achieve the project schedule and budget. Each option's success is driven by multiple quantifiable factors.

What should the project manager do to evaluate and select the best option based on costs and probabilities?

Options:

A.

Perform a FMECA fault tree analysis

B.

Conduct a sensitivity analysis

C.

Perform a decision tree analysis

D.

Conduct an analytic hierarchy process

Question 3

A project manager has finished the project charter for a project and has now moved into the planning phase. In the first planning meeting, the project manager is trying to determine the risk tolerance and risk attitudes of the project's key stakeholders.

What is the first resource the project manager should reference?

Options:

A.

Benefits management plan

B.

Enterprise environmental factors (EEFs)

C.

Project charter

D.

Requirements management plan