Winter Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

Newly Released PMI PMI-RMP Exam PDF

Page: 6 / 16
Total 221 questions

PMI Risk Management Professional (PMI-RMP) Exam Questions and Answers

Question 21

The project manager reviews project risks with the risk manager to update, monitor, and close risks in the risk register. The project manager determines one of the risks has a residual risk.

How should the risk manager document the impact of the residual risk?

Options:

A.

Utilize change management tools to request a budget increase from the project sponsor and update the risk register.

B.

Change the risk identification and description on the risk register to reflect the fact that the residual risk has materialized.

C.

Close the risk's status on the risk register since the residual risk has now materialized.

D.

Review the impact of the residual risk against the budget reserves and document the update in the risk register.

 

Question 22

While developing a risk management plan for a complex program in a metricized environment, a program management team is itemizing a response plan for each identified risk that appears in the risk register. What should the risk manager do to effectively monitor the risks?

Options:

A.

Present the complicated nature of the program risk responses to the sponsor for proper advice.

B.

Determine the workarounds for the program risks and allocate responsibilities to the team.

C.

Allow the most experienced program manager to handle the most critical program risks.

D.

Encourage the program team to assume risk ownership prior to delegation.

 

Question 23

A project team identifies that there is a probability of missing a key milestone in a project. The team wants to move forward with the risk response planning.

What should the risk manager complete first?

Options:

A.

The risk categorization

B.

The risk simulation

C.

The full risk description

D.

The risk response plan

Question 24

 

A new company initiates a project to incorporate a cybersecurity team. Which three documents should the risk manager analyze first? (Choose 3)

Options:

A.

Industry's standard procedures

B.

Current request for proposal (RFP)

C.

Company's historical financial reports

D.

IT infrastructure, networks, and data information

E.

Government laws and regulations

 

Page: 6 / 16
Total 221 questions