The project manager reviews project risks with the risk manager to update, monitor, and close risks in the risk register. The project manager determines one of the risks has a residual risk.
How should the risk manager document the impact of the residual risk?
While developing a risk management plan for a complex program in a metricized environment, a program management team is itemizing a response plan for each identified risk that appears in the risk register. What should the risk manager do to effectively monitor the risks?
A project team identifies that there is a probability of missing a key milestone in a project. The team wants to move forward with the risk response planning.
What should the risk manager complete first?
A new company initiates a project to incorporate a cybersecurity team. Which three documents should the risk manager analyze first? (Choose 3)