Easter Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

PMI PMI-RMP Questions Answers

Page: 17 / 17
Total 221 questions

PMI Risk Management Professional (PMI-RMP) Exam Questions and Answers

Question 65

The project team recorded a risk in the risk register indicating that weather-related delays may impact equipment delivery during project execution. When it is time to request the equipment shipment there is bad weather, but the client wants the equipment delivered anyway.

What should the project manager do?

Options:

A.

Wait until the weather improves before sending the equipment.

B.

Ask the project sponsor to approve shipping the equipment.

C.

Proceed with the planned risk response to move the equipment.

D.

Request the shipment of the equipment to satisfy the client.

Question 66

A project manager is assigned to a new project and is told they need to develop the project's risk register. When should the project manager identify the project risks?

Options:

A.

Identify risks only at the project's midpoint for the stakeholders to review them

B.

Ensure project team members proactively identify risks throughout the project to plan for possible response strategies

C.

Identify risks at the beginning of the project because the risk posture will not change

D.

Delegate risk identification to each team member and have them record the risks on separate risk registers for their areas

Page: 17 / 17
Total 221 questions