New Year Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

PMI CAPM PMI-002 New Questions

Page: 23 / 28
Total 748 questions

Certified Associate in Project Management (CAPM) Certification Questions and Answers

Question 89

A project plan is:

Options:

A.

A formal, approved document used to guide both project execution and project control.

B.

A document issued by senior management that provides the project manager with the authority to apply organizational resources to project activities.

C.

A narrative description of products or services to be supplie

D.

A document describing the organizational breakdown structure of the company.

Question 90

The process that is not a part of time management is:

Options:

A.

Define Activities

B.

Resource Planning

C.

Develop Schedule

D.

Sequence Activities

Question 91

Staffing requirements do not define:

Options:

A.

What types of skills are required

B.

What time frames

C.

What kinds of individuals or groups

D.

What type of resource planning is required

Question 92

A Reserve Analysis is a technique for:

Options:

A.

Estimate Activity Durations

B.

Estimate Activity Resources

C.

Sequence Activities

D.

Define Activities

Page: 23 / 28
Total 748 questions