Which of the following methods is a technique used to predict project duration by analyzing which sequence of activities has the least amount of scheduling flexibility?
You are assigned to a project that has already been decided to be outsourced. As a project manager, you need to organize a formal bid process and select the vendor for this project. Your senior management is forcing you to select a vendor which has good relation with your senior management. What is the BEST course of action for you?
Which of the following describes tool/ technique where expenditure of funds is reconciled with the funding limits imposed by the performing organization?
You are a project manager for your organization. Management has asked you to help them determine which projects should be selected for implementation. In a project selection model, which one of the following is the most important factor?