Question 77

A RAM is:

Options:

A.

Random access memory

B.

Rapid and movement

C.

Responsibilities and methods

D.

Responsibility assignment matrix

Question 78

Which of the following is NOT an example of a type of schedule report?

Options:

A.

Gantt chart

B.

Milestone chart

C.

fishbone diagram

D.

network diagram

Question 79

A complex project will fit best in what type of an organization?

Options:

A.

Functional

B.

Cross-functional

C.

Matrix

D.

Balanced

Question 80

Constraints do not include:

Options:

A.

Impacts of weather

B.

Organizational structure of the performing organization

C.

Collective bargaining

D.

Expected staff assignments