Question 61

Which of the following is true concerning the evaluation criteria?

Options:

A.

Can often be found in procurement documents

B.

Can be objective or subjective

C.

Used to rate or score proposals

D.

All of the above

Question 62

Projects are typically authorized as a result of any of the following except:

Options:

A.

Market demand

B.

Successful RFP bidding

C.

Regulatory requirement

D.

Technological advance

Question 63

The overall intentions and direction of an organization with regard to quality as formally expressed by top management is a __________.

Options:

A.

Quality Plan

B.

Quality Statement

C.

Quality Policy

D.

TQM

Question 64

A work breakdown structure is a ______.

Options:

A.

Result of the Collect Requirements process

B.

Deliverable oriented grouping of project elements that organizes and defines the total scope of the project

C.

Structure that can be used to track the project's time, cost, and quality performance against a defined baseline

D.

Valuable communications tool, but cannot be used to establish the number of required networks for Control Costs