Question 41

Bar charts generally illustrate:

Options:

A.

Progress of status.

B.

The critical path.

C.

Budget relation ships.

D.

Logical relationships.

Question 42

You are in the process of numerically analyzing the effects of identified risks. Which of the following are NOT tools or techniques you can use in the process?

Options:

A.

Sensitivity analysis

B.

Reserve analysis

C.

Expected monetary value analysis

D.

Modeling and simulation

Question 43

The responsibility assignment matrix is a project management tool used to ________.

Options:

A.

Ensure team members understand their specific roles.

B.

Develop the work breakdown structure based on available resources.

C.

Establish project members availability to work on the project.

D.

Depict the project's organizational structure.

Question 44

You are a project manager with several years of experience in project management. You have just accepted your first project in a foreign country. You have been in the country a week or two and are experiencing some disorientation. This is known as which of the following?

Options:

A.

Collocation

B.

Diversity shock

C.

Global culturing

D.

Culture shock