Question 105

A document or tool which describes when and how human resources will be brought onto and taken off the project team is called ____________.

Options:

A.

Staffing Management Plan

B.

Responsibility Assignment Matrix (RAM)

C.

Organizational Breakdown Structure (OBS)

D.

Resource Assignment Chart

Question 106

Life cycle costing __________________.

Options:

A.

Includes acquisition, operating, and disposal costs when evaluating various alternatives

B.

Includes only the cost of the development or acquisition of a product or service

C.

Does not take into consideration the effect of project decisions on the cost of using the resulting product

D.

Botn B and c are correct

Question 107

Which of the following statements concerning compromise as a conflict resolution is false?

Options:

A.

Neither party wins but both parties get some degree of satisfaction.

B.

Important aspects of the project may be hindered in order to achieve personal objectives.

C.

Compromise is generally considered a lose-lose situation.

D.

A definitive resolution is seldom achieved.

Question 108

Risks are accepted when ___________.

Options:

A.

You develop a contingency plan to execute should the risk event occur

B.

You accept the consequences of the risk

C.

You transfer the risk to another party

D.

Both A and B