Certified Associate in Project Management (CAPM) Certification Questions and Answers
Question 85
A Reserve Analysis involves:
Options:
A.
Estimating by multiplying the quantity of work by productivity rate
B.
Adding resource reserves to the activity resource estimates
C.
Developing project schedule with contingency reserves as a recognition of the schedule risk
D.
Incorporating time buffers into the activity duration estimates
Answer:
D
Explanation:
Explanation:
Reserve Analysis ( Contingency ): Project teams may choose to incorporate an additional time frame, called time reserve, contingency or buffer, that can be added to the activity duration or elsewhere in the schedule as recognition of schedule risk.
Question 86
A _______ is a series of actions bringing about a result.
Options:
A.
Project plan
B.
Process
C.
Schedule
D.
Flowchart
Answer:
B
Explanation:
Explanation:
Process
Question 87
A Project Scope Management includes :
Options:
A.
Initiation
B.
Project Plan Execution
C.
Overall Change Control
D.
Report Performance
Answer:
A
Explanation:
Explanation:
Project scope management includes: Initiation, Collect Requirements, Define Scope, Verify Scope and Control Scope
Question 88
What is not among the tools and techniques of an Organizational Planning?
Options:
A.
Staffing management plan
B.
Templates
C.
Human resource practices
D.
Organizational theory
Answer:
A
Explanation:
Explanation:
Staffing management plan is not tools and techniques of an Organizational Planning. Other options are true.