Certified Associate in Project Management (CAPM) Certification Questions and Answers
Question 73
Activity Resource Requirements is an input to ____________ :
Options:
A.
Estimate Activity Durations
B.
Control Schedule
C.
Sequence Activities
D.
Estimate Activity Resources
Answer:
A
Question 74
All are output of verify scope.
Options:
A.
Precedence diagramming method (PDM)
B.
Arrow diagramming method (ADM)
C.
Expert judgment
D.
Network templates
Answer:
C
Explanation:
Explanation:
Expert judgment is not used in Sequence Activities. Sequence Activities : Identifying and documenting interactivity logical relationships.
Question 75
A Reserve Analysis technique is NOT used during __________.
Options:
A.
Control Costs
B.
Estimating Activity Duration
C.
Determine Budget
D.
Estimate Costs
Answer:
A
Explanation:
Explanation:
Reserve analysis is used during Estimate Costs to calculate contingency buffers that apply to individual or group of activities. Reserve analysis is used during Determine Budget to calculate management contingency buffers that apply to the entire project. Reserve analysis is done during Activity Duration estimation in order to calculate duration buffers for individual or group of activities.
Question 76
Which of the following is an output of a Verify Scope process?