New Year Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

PDF PMI-002 Study Guide

Page: 7 / 28
Total 748 questions

Certified Associate in Project Management (CAPM) Certification Questions and Answers

Question 25

Which of the following is useful in Identify Risks because it permits a systemic evaluation of the work?

Options:

A.

Work breakdown structure.

B.

Design specification

C.

Project flow chart

D.

Project chart

Question 26

You are project manager and the monthly report to the client showed zero schedule variance. However, member of the team know that a milestone has been missed which will cause an overall delay to the project. Which one of the following is being inadequately reported?

Options:

A.

Communication plan variance

B.

Resource management plan

C.

Critical path status

D.

Risk analysis

Question 27

To determine the impact of a change that has occurred, which of the following should be taken?

Options:

A.

Re-evaluate the work breakdown structure.

B.

Assess the communication policy.

C.

Review the earned value

D.

Performance measurement

Question 28

You have been assigned to take over a project that is 60 percent complete according to the schedule. After evaluation, you find that the project is running far behind schedule, and that the project will probably take double the time originally estimated by the previous project manager. However, the sponsor has been told that the project is on schedule. What is the BEST course of action you will take?

Options:

A.

Add new resource to the project and complete the project on schedule.

B.

Show your evaluation to sponsor.

C.

Ask your senior manager to deal with this.

D.

Turn the project back to the previous project manager.

Page: 7 / 28
Total 748 questions