Which of the following can be used to help you or other project managers on future projects?
A company is building a global monitoring network in 40 countries. The program completes the planning phase and a review is conducted of the program components’ strategic alignment with the intended program and company goals. The review identifies issues that should be resolved to improve program progress. One of the issues identified is the lack of incorporation of both software and configuration management tools.
Which of the following must be addressed?
You are a program manager for a large construction program. You need to ensure that the projects in the program are in accordance with the schedule. You are tracking start and finish dates for them. Which of the following processes are you on?
You are the program manager for your organization and are working with Tracy, one of the project managers in your program. Tracy is having some trouble understanding the concept of the critical path in her project's network diagram. Which one of the following is the best definition of the critical path?