New Year Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Helping Hand Questions for PgMP

Page: 16 / 17
Total 452 questions

Program Management Professional (PgMP) Questions and Answers

Question 61

You are the program manager for your organization. Management has asked that you determine when resources, such as leased equipment, are no longer needed so that you may release the resources to save time, money, and utilization of resources within your program. What program management process is management asking you to perform?

Options:

A.

Contract administration

B.

Resource management

C.

Resource control

D.

Procurement management

Question 62

A program manager, who reports to a company's CIO, is responsible for managing a strategic initiative program. During a program review meeting, the CIO informs the program manager about potential budget cuts that would impact program resources, and urges the program manager to begin delivering benefits more quickly to continue the program.

What should the program manager do first?

Options:

A.

Update the benefits management plan, and send it to stakeholders for review.

B.

Document the impact on the program, then present the findings to the steering committee to determine next steps.

C.

Conduct a risk assessment associated with an accelerated schedule, update the risk register, and request steering committee approval.

D.

Revise the program schedule to adapt to an accelerated delivery of benefits, and present it to the steering committee for approval.

Question 63

What does CPI value less than 1.0 indicates?

Options:

A.

Cost overrun for work completed

B.

Scheduled performance is great

C.

Cost underrun of performance to date

D.

Cost for completed work is as per estimate

Question 64

You are the program manager of the GHY Program. Your program team has identified a risk dealing with the materials you will be using in the program. It is possible that if the materials are not installed properly they will cause serious damage in future phases of the program. Your team has recommended additional training and a consultant to help the team members install the material accurately to reduce the likelihood of the risk event. You agree and the team executes the risk response. What type of risk response have you implemented in this situation?

Options:

A.

Enhancing

B.

Workaround

C.

Mitigation

D.

Avoidance

Page: 16 / 17
Total 452 questions