Question 53

An organization requests that a junior project manager, with no previous experience or training in the industry, take over a complex program component. The program component involves senior subject matter experts and has dependencies with other large projects to deliver key benefits to the organization.

How should the junior project manager respond to this request?

Options:

A.

Accept the assignment, identify the skill gaps, and request training.

B.

Reject the assignment, because of the ethical requirement not to accept work for which the project manager is not qualified.

C.

Accept the assignment as a challenge and an opportunity to acquire new skills and seek advice from a senior project manager.

D.

Reject the assignment because of fear of failure and resulting negative career impact.

Question 54

The program charter for a new, five-component program has been approved.

What should the program manager use to communicate the program's intended direction and the linkage between organizational strategies and planned work?

Options:

A.

Program roadmap

B.

Program charter

C.

Program business case

D.

Program management plan

Question 55

When a change enters your program requirements you must update all of the following documents except for which one?

Options:

A.

Program work breakdown structure

B.

Program activity list

C.

Program charter

D.

Program scope

Question 56

After an organization initiates a strategic program, several project managers express interest in joining the program team. The program manager’s supervisor recommends a list of project managers to be part of the team.

What should the program manager do to select the project managers?

Options:

A.

Complete a skill set inventory and select the most suitable resource(s)

B.

Ask interested project managers for their CV or résumé and conduct interviews

C.

Accept the recommendation of the program manager’s supervisor

D.

Contact the human resource manager for project managers’ availability