A program has a BAC of $550,000 and is currently 45 percent complete though was actually scheduled to be 55 percent complete by this time. The program has spent, however, $265,000 to date. Based on this information what is the cost performance index (CPI) for this program?
You are the program manager for your organization. Your program has recently completed its program scope and you've transferred the benefits to the operations of your organization. Before your program is considered closed you must complete some forms and procedures as required by your organization. The requirements to complete the forms and paperwork are also known as what?
A program to implement a company's new system is nearing completion and the program manager attempts to close the program. However, despite training provided to the operational staff on the new system, there is concern that the defined expected benefits will not be fully realized.
To prevent this concern in the future, which of the following should occur?
Which project management meeting allows stakeholders to meet one another and to learn about the project?