Winter Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

PgMP Exam Dumps : Program Management Professional (PgMP)

PDF
PgMP pdf
 Real Exam Questions and Answer
 Last Update: Mar 3, 2025
 Question and Answers: 452
 Compatible with all Devices
 Printable Format
 100% Pass Guaranteed
$29.75  $84.99
PgMP exam
PDF + Testing Engine
PgMP PDF + engine
 Both PDF & Practice Software
 Last Update: Mar 3, 2025
 Question and Answers: 452
 Discount Offer
 Download Free Demo
 24/7 Customer Support
$47.25  $134.99
Testing Engine
PgMP Engine
 Desktop Based Application
 Last Update: Mar 3, 2025
 Question and Answers: 452
 Create Multiple Test Sets
 Questions Regularly Updated
  90 Days Free Updates
  Windows and Mac Compatible
$35  $99.99

Verified By IT Certified Experts

CertsTopics.com Certified Safe Files

Up-To-Date Exam Study Material

99.5% High Success Pass Rate

100% Accurate Answers

Instant Downloads

Exam Questions And Answers PDF

Try Demo Before You Buy

Certification Exams with Helpful Questions And Answers

Program Management Professional (PgMP) Questions and Answers

Question 1

A program manager is concerned because several change requests in a component project are causing delays to the program's work package milestones. There are insufficient skilled resources within the component project to complete both the change requests and the milestone tasks.

What should the program manager do next to address this risk?

Options:

A.

Prioritize which resources are critical to the project based on an impact analysis of the critical change requests and update the program roadmap.

B.

Prioritize which change requests are critical to the project based on an impact analysis, resource only critical change requests until overdue milestones are achieved, and update the risk register.

C.

Mandate that no component project change requests will be processed until overdue milestones have been completed and update the risk register to reflect this.

D.

Add the lack of skilled resources to facilitate the large number of change requests to the issue log.

Buy Now
Question 2

A program manager for the construction of a ship reviews the program management plan with a shipyard representative. The shipyard representative indicates that while 65 percent progress was anticipated, only 60 percent has been achieved.

What should the program manager do to ensure benefits realization?

Options:

A.

Conduct a program performance analysis based upon the deviation, and update the program business case to reflect the schedule delay.

B.

Inform the program sponsor and the steering committee of the delay, and validate the program business case.

C.

Analyze the impact of the delay, review risks identify any corrective actions, and update the benefits management plan.

D.

Update the program schedule, and escalate the issue to the program management office (PMO) to accelerate shipyard work.

Question 3

Which project management meeting allows stakeholders to meet one another and to learn about the project?

Options:

A.

Project scope review

B.

Project authorization meeting

C.

Project status meeting

D.

Project kick-off meeting